Renovation Scope & Site Parameters
Civil & Finishes
850 sq.ft
sq.ft
Minor / Cosmetic Refresh
Repainting, minor plaster repair, wood polishing, switchboard replacement
Moderate Remodel (Recommended)
Tile flooring overlay, plumbing updates, bathroom tiling, kitchen countertop
Full Civil Gut Renovation (Bare Shell)
Demolition to brick, rewiring, re-piping, floor hacking, waterproofing & masonry
Dedicated Wet-Area Overhauls
@ ₹80k ea
Tiling, waterproofing, diverters & fittings
₹
Dado tiles, sink, granite platform & gas lines
10%
%
For unexpected seepage, rotting or masonry
₹
Chute, tractor transport & municipal dumping
Society By-Laws: Most cooperative housing societies (CHS) charge refundable renovation deposits (₹25,000 - ₹50,000) and permit noisy drilling works strictly between 9 AM and 6 PM on weekdays.
Total Renovation Budget
₹ 12,34,750
Includes 10% Reserve (₹1,12,250)
Effective Cost / Sq.Ft
₹ 1,453
Moderate Remodel
Materials Share (~60%)
₹ 6,73,500
Tiles, cement, plumbing, wires, paint
Labor & Masonry (~40%)
₹ 4,49,000
Plumber, electrician, mason, painter
Renovation Outlay Breakdown
Cost CentersRenovation Budget Ledger
| Trade / Renovation Activity | Allocation | Basis | Amount (₹) |
|---|---|---|---|
| Main Civil & Finishes Work Moderate Remodel | Civil Work | 850 sq.ft @ ₹950 | ₹ 8,07,500 |
| Bathroom Overhauls 2 Bathrooms complete | Wet Area | ₹80k per bath | ₹ 1,60,000 |
| Kitchen Platform & Civil Plumbing Granite counter & sink lines | Wet Area | Fixed Scope | ₹ 1,20,000 |
| Demolition, Chute & Debris Hauling Municipal disposal | Logistics | Lump Sum | ₹ 35,000 |
| Unforeseen Contingency Reserve 10% buffer for structural surprises | Risk Buffer | 10% of subtotal | ₹ 1,12,250 |
| Total Renovation Cost | ₹ 12,34,750 | ||